News

RESPONSE TO NPA REVIEW OF SNOWY 2.0 ENVIRONMENTAL PERFORMANCE

12/04/2024

Snowy Hydro acknowledges and thanks the National Parks Association of NSW’s ongoing attention to matters relevant to Kosciuszko National Park, including the construction of Snowy 2.0.

As a longtime operator of the Snowy Scheme within Kosciuszko National Park, we recognise the park is a sensitive environment with high conservation values that require protection. We continue to seek ways to make positive contributions to Kosciuszko National Park through actions such as road improvements and a $100 million investment to improve the biodiversity and recreational values of the park. 

Snowy Hydro takes its environmental management obligations very seriously and we are absolutely committed to ensuring that the construction and operation of Snowy 2.0 is carried out in a manner that is compliant with all applicable laws and project approvals. 

The NPA refers to Snowy 2.0 environmental management plans, the project’s Independent Environmental Audits (IEAs), and state government compliance actions.

There are six management plans yet to be approved and these relate to the management of environmental impacts during the Snowy 2.0 commissioning and operations phase only, which is a couple of years away, not current construction activities. Despite this, progress of each of these plans is well advanced and are either awaiting input from relevant stakeholder organisations or are being revised following formal feedback. Snowy Hydro is actively engaging with the Department of Planning, Housing and Infrastructure (DPHI) on the progress of each plan.

Snowy Hydro undertakes more IEAs than are required under the project approvals due to the sensitive nature of the environment and the scope of the Snowy 2.0 project. Of the 12 non-compliances identified from 372 elements assessed under the most recent IEA,  none caused any actual harm and all are being rectified as a matter of priority.  

The Snowy 2.0 project has been the subject of several compliance actions by EPA and DPHI over the last two years and in each case, important lessons have been learned that have informed improvements to policies, procedures and site practices. Snowy Hydro continues to take these matters very seriously and implement steps to ensure that identified incidents do not happen again. 

Snowy 2.0, a pumped-hydro expansion of the Snowy Scheme, will provide 2,200 megawatts of on-demand, dispatchable energy and almost a week of renewable energy storage to help maintain grid security and reliability while enabling Australia’s decarbonisation.

News

HAVE YOUR SAY: SNOWY HYDRO LAUNCHES COMMUNITY INSIGHTS CAMPAIGN 

05/04/2024

Snowy Hydro is launching a community insights campaign to better understand the social impacts of the Snowy 2.0 project.

The campaign seeks to engage and connect with community members across south-eastern NSW to gather insights, opinions, and experiences related to Snowy Hydro operations and the Snowy 2.0 project.

Through an online survey available at www.snowyhydro.com.au/haveyoursay, we invite residents, stakeholders, and interested parties to share their perspectives and help shape the future of their communities. A series of focus groups, one-on-one meetings, phone surveys and community pop-up stalls will support the online survey.

“This campaign reiterates Snowy Hydro’s commitment to transparent and inclusive community engagement,” said Snowy Hydro CEO Dennis Barnes. 

“We value the input of our community members and recognise the importance of understanding their needs and concerns.”

The survey, which will be open until 5 May 2024, covers a range of topics, including community sentiment, perceptions of the Snowy 2.0 project, and suggestions for improving Snowy Hydro’s community engagement efforts. Participation is open to individuals aged 18 and above who reside or own property in the Snowy Monaro, Snowy Valleys, Towong, Bega Valley and surrounding local government areas.

“We encourage you to take part in this survey and contribute to the dialogue surrounding the Snowy 2.0 project and its impact on our communities,” added Mr Barnes. 

“Your feedback will be important in informing Snowy Hydro’s social impact strategy and community engagement initiatives.”

Throughout April, Snowy Hydro representatives will engage with stakeholders in key regional towns, fostering open conversations about Snowy Hydro’s operations and future priorities. The consolidation of survey findings is planned for June 2024, with a publication of key results expected in July 2024.

For more information or to participate in the survey, please visit www.snowyhydro.com.au/haveyoursay.

Additionally, feedback or inquiries can be directed to Snowy Hydro via phone at 1800 623 776 or email at community@snowyhydro.com.au

News

SNOWY 2.0 PROJECT UPDATE – MARCH 2024 

03/04/2024

This month we’ll update you on tunnel boring machine (TBM) Kirsten, which is putting Snowy 2.0 at the forefront of TBM tunnelling innovation, along with the unique concrete segments she will install as part of the inclined pressure shaft excavation and lining.

Damon Miller, Senior Engineering & Quality Manager for Snowy 2.0, works with the design, manufacturing and construction teams to plan and deliver the engineering solutions behind Snowy 2.0, the pumped hydro expansion of the Snowy Scheme.

Building the inclined pressure shaft (IPS) will be a unique and technically challenging engineering feat for the project team

After finishing the 2.9 kilometre Emergency Cable and Ventilation Tunnel, TBM Kirsten has been substantially modified for her next critical role excavating the IPS.

This very steep, 1.6 kilometre, 10 metre diameter shaft forms part of the waterway and will connect the headrace tunnel with the underground power station. 

Project director Dave Evans believes the specially manufactured segments being used for this shaft are going to change the world of hydropower. “It means we can do less steel lining, we can move power stations closer to the surface which is what we’ve done here and construct an inclined pressure shaft with a tunnel boring machine which all makes it safer, quicker and the quality a lot better.”

To see the latest Snowy 2.0 project statistics, view the fact sheet here.

To cope with the extreme and fluctuating water pressures in the IPS, the concrete segment rings lining the tunnel require bespoke connectors.

The Force Activated Coupling System or FACS are specially-developed steel couplers with pin and socket elements.

When the segment rings are interlocked, the pre-stressed FACS keep the joint closed when the tunnel experiences sharp changes in pressure from turbine operations and shut downs. It’s like water hammer when opening or closing a tap at home, just on a much larger scale.

This new technology has been developed by Future Generation joint venture partner Webuild and their designer Lombardi, with the FACS segments being manufactured at our precast factory in Cooma.

A large-scale test is being conducted by installing eight FACS rings to link the emergency, cable and ventilation tunnel with the IPS.

Meanwhile, innovative design by the leading TBM manufacturer Herrenknecht has allowed TBM Kirsten to be modified to safely tunnel uphill.

The machine’s working platforms, equipment and operator’s cabins all pivot to remain horizontal and the walkways become steps and ladderways. 

A screw conveyor will move excavated rock from the cutterhead. This feeds into a sandwich conveyor that has face-to-face rubber belts to hold the material so it can be transported down the steep slope without spillage.

The IPS is on a 47% incline so a monorail is being installed to transport workers and there is a rack and pinion system for multi-service vehicle access including segment delivery up the steep slope to the TBM.

News

JOIN US FOR SNOWY 2.0 COMMUNITY INFORMATION SESSIONS

08/03/2024

If you’re interested in the latest updates from the Snowy 2.0 project, come along to information sessions being held throughout the Snowy Mountains this month.

The Snowy 2.0 delivery team, led by Snowy Hydro, is hosting events in Talbingo, Tumut, Tumbarumba, Adaminaby and Cooma, with opportunities to find out more about the project, ask questions and provide your feedback.

These in-person events will cover a range of topics including:

  • project news and construction activities 
  • engineering innovations and manufacturing
  • traffic management, environment and safety
  • accommodation, recreation access and other local issues; 
  • local suppliers, jobs and training on Snowy 2.0.

Snowy Hydro CEO Dennis Barnes said it was essential local people were updated about progress on Snowy 2.0 and that they understood the significance of the project.

“What’s being constructed right here in the mountains is a critically important renewable energy project that will help maintain Australia’s grid security and reliability well into the future,” Dennis said. 

“It is a large and complex project that’s also generating jobs and significant investment in regional areas.

“We’re committed to keeping our local communities informed about Snowy 2.0 and responding to any concerns. We are available to answer questions at our information sessions so I encourage people to come along to hear from the project team directly.”

The Snowy 2.0 community information sessions are held twice yearly. Some are drop-in sessions, with the chance to speak one-on-one with project team members from Snowy Hydro and principal contractor Future Generation Joint Venture. Other events feature a formal presentation followed by community Q&As.

Community information sessions schedule:

Date Town and locationTime
Thursday 14 March 2024
Thursday 14 March 2024
Talbingo shops
Tumut River Brewing Co
12pm – 2pm
6pm – 7.30pm
Friday 15 March 2024Near Tumbarumba IGA, The Parade12pm – 2pm
Wednesday 20 March 2024Adaminaby Bowling Club6pm – 7.30pm
Thursday 21 March 2024Cooma Car Club6pm – 7.30pm
News

100,000 SNOWY 2.0 TUNNEL SEGMENTS LOCALLY MANUFACTURED

29/02/2024

The Snowy 2.0 Cooma precast manufacturing facility has hit another significant milestone and completed production of 100,000 of the 130,000 concrete segments needed to line 27 kilometres of tunnels for the pumped-hydro megaproject. 

More than 230,000m3 (or more than 550,000 tonnes) of concrete has been used to manufacture these seven-tonne precast segments, installed by the three tunnel boring machines (TBMs) used on the Snowy project. 

Snowy Hydro CEO Dennis Barnes said it was pleasing for the project to be manufacturing and investing locally, while also providing employment opportunities. 

“About 200 people from the 3,000-strong Snowy 2.0 workforce work at the precast factory operated by our project contractor Future Generation Joint Venture,” Dennis said. “The facility supports local employment and also on-the-job training for a number of school-based apprentices from Monaro High.”   

The precast facility includes a concrete batching plant and onsite laboratory to check the quality of every segment produced. Many of the raw materials like aggregates are sourced from local quarries at Mt Mary and Nimmitabel.

Careful consideration and design of the concrete mix, which includes waste material, has meant significant reduction in the environmental production footprint while improving the segments’ durability and performance.

Carousels utilising robotics to automate the process of demoulding, cleaning and application of the release agent on the segment moulds have been used in the manufacturing process.

One of the two carousels has now been modified to produce the precast segments for the Snowy 2.0 inclined pressure shaft (IPS). This very steep 1.65km shaft will be excavated by TBM Kirsten and will link the underground power station with the headrace tunnel coming from Tantangara.

The IPS segments involve a world-first force-activated coupling system (FACS) designed to withstand the powerful internal forces of water moving through the 10-metre diameter inclined tunnel.

Installing segments with FACS eliminates the need for a second tunnel lining, thereby improving the quality, safety and the rate of tunnel completion. 

The Snowy 2.0 precast factory will produce approximately 9,000 IPS segments, with nine used in each tunnel-lining ring. The first ring prototype has been completed, with mass production expected to start next month.

FAST FACTS


News

SNOWY 2.0 PROJECT UPDATE – FEBRUARY 2024

28/02/2024

The new Snowy 2.0 power station will boast the latest in hydro technology, delivered by our expert subcontractor Voith Hydro. In the latest project update, Snowy 2.0 mechanical engineer Mahali Heffner details how quality assurance activities and factory acceptance testing is carried out on each power station component.

Every one of the hundreds of pump-turbine-generator components undergoes rigorous testing before it leaves the Voith factory. This is to ensure they meet high quality standards and will operate reliably when the power station is switched on.

A team of Snowy Hydro and independent assessors recently conducted mechanical and hydraulic dimensional checks on the first Snowy 2.0 runner at the Voith factory in Shanghai, China.

The runner is the heart of a hydro turbine – it’s the rotating element that drives the generator to produce power.

Acceptance testing includes checking the profile of the blades and surface examinations.

Dye penetrant testing is used to identify imperfections on the surface of the 31 tonne, 4.2 metres-wide runner. We spray on a red dye, clean it and apply the developer. If imperfections are present, the dye will make them visual.

Snowy Hydro and contractor Future Generation Joint Venture (FGJV) work with Voith and other subcontractors on a range of quality assurance activities as part of the multi-stage manufacturing process.

At Lobs Hole in the Snowy Mountains, power station components including turbine guard valves, spiral cases and draft tube liners are being progressively delivered to site.

Meanwhile, deep underground, excavation of the machine hall and transformer hall cavern crowns have been completed and we’ve almost finished the final side slashing to widen the structures. Drill and blast works are also continuing in the cross passages and tunnels that are an important part of the power station complex.

At the other end of the project at Tantangara, the intake is really starting to take shape. We are well into stage two of the excavation, now approximately 49 metres below ground level and approximately six metres to go. 

We map the cut face to determine what rock support is required and then after the design is confirmed, rock bolts and shotcrete are installed. It’s exciting to see the shape of the transition from intake to tunnel, with the canopy tube rock support in the intake face forming an arch above the tunnel entrance. 

Drill and blast of the tunnel excavation is scheduled to start soon and the first milestone target will be to link up the intake with the gate shaft. 

News

SNOWY 2.0 PROJECT UPDATE – JANUARY 2024 

31/01/2024

Deep underground at Lobs Hole in the Snowy Mountains is the heart of Snowy 2.0, the pumped-hydro expansion of the mighty Snowy Scheme. It’s where we’re building a huge power station complex that will house equipment capable of generating 2,200 megawatts of renewable energy.

In this month’s update we’re celebrating a major power station construction milestone – the breakthrough blast of the machine hall cavern crown.

With excavation of the crown – or ceiling – of the cavern taking place from both ends, the final three metres of rock are drilled and charged with explosives according to a precise blast plan.

The tunnels are cleared and the shotfirer arms the electronic blasting system which uses a unique electrical pulse to initiate firing of the explosives.

According to Snowy 2.0 project director Dave Evans, the machine hall achievement signals further progress after the recent transformer hall cavern crown breakthrough and restart of tunnel boring machine Florence in the headrace tunnel at Tantangara.

“These milestones are only possible with the whole team working together as one, whether they are subcontractors like Orica, the company managing underground blasting operations, or the lead contractor Future Generation and Snowy working so closely together.”

To see the latest Snowy 2.0 project’s statistics, view the fact sheet here.

As the underground drill and blast works continue, the manufacturing of major hydropower components for Snowy 2.0 is also well underway.

Snowy Hydro senior quality engineer Victor Teo is based for part of the year in Shanghai, where Voith Hydro – the company producing major power station equipment for Snowy 2.0 – has a large facility. 

He also travels to nearby cities including Zhuji and in his quality and compliance role, participates in factory acceptance tests and hold point inspections for components being fabricated by subcontractor Shenke such as the draft tube liners and cones, and the huge stator frames.

The draft tube liners funnel water into and out of the power station turbines and are comprised of six segments. They are 4.6 metres high, 30 metres long and weigh 40 tonnes when assembled.

The six stator frames that house the generator are fabricated in two halves and are welded together for a total weight of more than 400 tonnes. 

Snowy Hydro has an integral part to play in establishing high standards of equipment manufacturing, which meet the engineering requirements for our critical Snowy 2.0 project infrastructure.

News

BREAKTHROUGH MILESTONE FOR SNOWY 2.0

05/01/2024

Snowy Hydro is pleased to announce another major achievement for the Snowy 2.0 pumped-hydro project, with the breakthrough of the final three metres of the power station’s 223-metre long transformer hall cavern crown.

The Snowy 2.0 delivery team began excavating the transformer hall and machine hall caverns in June 2023. The Snowy 2.0 power station will be located approximately 800m underground at Lobs Hole in the Snowy Mountains. When completed, the machine hall will be 251 metres long and 52 metres high and the transformer hall 223 metres long and 46 metres high. Together they will form one of the largest and deepest caverns in the world, big enough to fit the Sydney Opera House inside. 

Precise drill and blast methods are used to profile the curved cavern crowns (or ceilings) and break up the rock, which is mucked out and followed by surface scaling to remove any remaining loose rock. The exposed solid rock face is then supported with rock bolts and shotcrete. The excavation sequence of the cavern crowns is carefully planned and executed, as the rock mass relaxes and moves inwards as the excavated void increases. These movements are expected and are closely monitored during the process.

So far, about 17,000 cubic metres of material has been excavated from the central heading of the transformer hall cavern crown. The heading has been advanced in 3-4 metre rounds from either end of the cavern for a total of 77 blasts.

The machine hall cavern crown breakthrough will take place in coming weeks, and widening of both cavern crowns, known as side slashing, is ongoing and planned for completion in coming months. Excavation of both power station caverns is set to continue through 2024. 

The breakthrough of the transformer hall cavern crown represents another important milestone for the Snowy 2.0 pumped-hydro project that will significantly expand the existing Snowy Scheme and will provide an added 2,200 megawatts of on-demand power and 160 hours of large-scale renewable energy storage for the National Electricity Market.

Snowy Hydro CEO Dennis Barnes said: “The breakthrough of the transformer hall cavern crown is a really pleasing milestone for the Snowy 2.0 team, reinforcing that we’re making good progress with our underground drill and blast excavation activities. We are well on our way to delivering the largest single project that will help ensure Australia’s secure and reliable transition to renewable energy.”

News

SNOWY 2.0 PROJECT UPDATE – JUNE 2023

26/06/2023

In the June update of the pumped-hydro expansion of the mighty Snowy Scheme, Snowy 2.0’s Alex Woschitzka explains construction progress at the massive Talbingo and Tantangara intakes. The project’s Quality Coordinator also checks in on the transformation of a narrow fire trail through steep terrain into a road suitable for heavy vehicles.

Significant progress has been made at the Talbingo intake, where water will exit the tailrace tunnel when Snowy 2.0 generates power. This is also where water enters the tunnel for pumping.

Construction teams have moved more than 310,000 cubic metres of earth to date, about half the total amount that will need to be moved. More than 24,000 metres of rock bolts have been installed and 8,300 square metres of shotcrete sprayed to support the wall.

As part of quality assurance, the shotcrete must be tested for compressive strength. Samples are taken from the truck and also cored from the face to ensure it meets the intended strength requirements. For the rock bolts, pull-testing is conducted to ensure they have been correctly installed, and meet the design and quality requirements. 

When completed, the total height of the Talbino intake excavation will be 104 metres, with about 31 metres of that below the water level. The concrete intake structure will be an impressive 50 metres in height.

Construction is well underway on an internal access road through mountainous terrain. With the help of Snowy 2.0 subcontractor Leed, a narrow fire trail will be widened into a six-kilometre road to enable heavy vehicles to access a rock emplacement area on Talbingo Reservoir.

Works began from both ends across very challenging terrain, achieving a major milestone recently when the two pioneering fronts joined across the Middle Creek cliffs. A temporary bridge with a 36-metre span has been installed across Middle Creek and is capable of supporting a fully-loaded 80-tonne dump truck.

In another milestone achieved in June, stage one earthworks have now been completed at the Tantangara intake. The first stage involved excavation of about 205,000 cubic metres of earth with a further 78,000 cubic metres of drilling and blasting earthworks expected in the next stage.

To support the excavation, more than 18,000 metres of rock bolts have been drilled and installed, and approximately 6,100 square metres of shotcrete sprayed. The excavation is currently about 26 metres deep and will be extended to a total depth of 55 metres.

Tantangara intake is where water will enter the headrace tunnel when the Snowy 2.0 power station is in generation mode. When in pumping mode, water will exit through the intake and fill Tantangara Reservoir. 

News

SNOWY 2.0 PROJECT UPDATE – MAY 2023

30/05/2023

May was a milestone month for the Snowy 2.0 team with the completion of the emergency, cable and ventilation tunnel, or ECVT – another vital step in the construction of Snowy Hydro’s new pumped-hydro expansion megaproject.

Snowy 2.0 senior project manager Rodd  Brinkmann explains the next stage of the project from his base at Lobs Hole, as preparation for excavation for the underground power station cavern gets underway.

The ECVT is a 2.93 kilometre tunnel that runs adjacent to the main access tunnel and provides alternate access to the site of the underground power station. Tunnel boring machine (TBM) Kirsten recently completed excavation of the ECVT and will soon start tunnelling the inclined pressure shaft. This very steep shaft links to the headrace tunnel from Tantangara Reservoir. 

TBM Kirsten will need to undergo modifications to excavate the 25-degree incline, including installation of a screw conveyor to extract excavated rock from the cutterhead to a sandwich conveyor system. With such a steep incline, construction of the 1.45km shaft with its concrete segment-lined tunnel, will be a world first. 

In the main access tunnel, or MAT, construction of cross passages and construction access tunnels is well underway with 850 metres of drill and blast tunnel excavation completed. Of the five cross passages linking the MAT and the ECVT, two are fully excavated and waiting on breakthrough into the ECVT.  Key construction tunnels are also being excavated to provide access to the machine hall, transformer hall and the top of the tailrace surge shaft. 

Workers have reached the main cavern areas from both ends and will soon commence excavation and support of the cavern crowns or ceilings of the power station halls. The excavation sequence of the cavern crowns is critical, as the in situ rock mass will relax and move inwards as the excavated void increases. These movements will be closely monitored during the process. Geotechnical drilling and plate load tests will measure and confirm the characteristics of the rock geology around the power station.

Dynamic 3D models of the power station caverns are also being used. 3D models are created using digital engineering to transform 2D design drawings and are displayed in the state-of-the-art immersive theatre at Snowy Hydro’s Discovery Centre in Cooma, where Snowy 2.0 engineers can collaborate with power station design experts from around the world. Once construction is complete, the detailed 3D models will be a valuable tool for asset maintenance. 

With so much activity in the tunnels, the current Snowy 2.0 underground workforce will increase by another 200 people in the coming months.  

News

SNOWY 2.0 – PROJECT UPDATE

03/05/2023

Snowy Hydro’s management team is working towards resetting the delivery timeline and budget for the Snowy 2.0 project with its principal contractor, Future Generation Joint Venture (FGJV), as part of an ongoing project review. 

The reset will ensure this critically important clean energy infrastructure project is placed on a robust and sustainable footing for FGJV to progress the schedule in a realistic and productive manner. 

While significant progress has been achieved by FGJV on Snowy 2.0, there are delays to Snowy 2.0’s contracted schedule and likely cost impacts beyond the contingency allowed, which remain under review by Snowy Hydro. 

There are four broad categories of factors contributing to schedule delays and likely cost increases: 

  • the mobilisation and resourcing implications of the COVID-19 pandemic; 
  • the effect of global supply chain disruption and inflation impacting the cost and availability of a skilled workforce, materials, and shipping; 
  • a number of design elements requiring more time to complete due to their technically complex nature, with the final design now being more expensive to construct; and  
  • the impact of variable site and geological conditions, with the most impactful being the soft ground encountered that is delaying tunnel boring machine (TBM) Florence’s progress at Tantangara.  

Snowy Hydro anticipates that the timeline for full commercial operation is delayed by a further 12-24 months from the current publicly released dates:

MilestoneEarliestLatest
First Power June 2027 – December 2027June 2028 – December 2028
Commercial operation of all units December 2028 December 2029

Snowy Hydro expects more detail on the budget implications of the project reset around July 2023, and this will be clearly communicated with key project stakeholders.  

Snowy Hydro CEO Dennis Barnes said: 

“Since joining Snowy Hydro earlier this year I have focused on ensuring our major projects are placed on a realistic and sustainable footing, while maintaining construction progress.  

“This project is critically  important to the transition of Australia’s electricity grid and it’s crucial that we are working to a safe, efficient and realistically achievable timeframe to enable orderly planning for all our stakeholders. I am committed to being transparent about our progress and how we are proactively managing the inevitable issues and challenges that arise in a complex project like this. 

“While many other major infrastructure projects have been impacted by the same challenges, Snowy 2.0 continues to make positive progress.

“Snowy 2.0 is providing significant employment and economic benefits both regionally and domestically. There are currently over 2,400 people employed on the project and thousands more jobs generated indirectly through supply chains and support services.

“TBM Kirsten has tunnelled 2.9 km to reach the underground power station cavern complex and we now have access to this site from both ends. We shortly expect to commence the 6km tailrace tunnel that will feed into Talbingo Reservoir and the excavation of intakes at Talbingo and Tantangara are proceeding very well.”

News

SNOWY 2.0 HEADRACE TUNNEL UPDATE

16/12/2022

Snowy 2.0 teams are monitoring a surface depression that has emerged above the headrace tunnel at Tantangara.

The integrity of the tunnel has not been compromised, and tunnelling is continuing while work to remediate the surface depression above tunnel boring machine (TBM) Florence is carried out. There is a safety exclusion zone around the surface depression.

Ensuring the safety of the Snowy 2.0 workforce and members of the public is the priority for Snowy Hydro and principal contractor Future Generation Joint Venture. 

The Snowy 2.0 teams are conducting geophysical investigations of the area and continuing grouting operations and probing from the TBM. 

As previously indicated, the ground conditions encountered by the TBMs on Snowy 2.0 have been highly variable, ranging from very loose, sandy ground to extremely hard rock in fluctuating groundwater conditions. 

TBM Florence is transitioning from soft material into harder rock conditions.