SNOWY 2.0 PROJECT UPDATE – OCTOBER 2023

08/11/2023

In this month’s project update, we check on tunnel excavation at Talbingo, progress at the upstream surge shaft at Marica, and we hear about the specialised drilling underway to prepare for services such as power and communications between Lobs Hole, Marica and Tantangara.

Will Binsted, Snowy 2.0 Lobs Hole Construction Manager, has been working on the project for four years and is responsible for coordinating both surface and underground works. Will, who lives locally in Tumut, liaises with technical specialists as well as designers and project engineers across the busy worksite.

To see the latest Snowy 2.0 project’s statistics, view the fact sheet here.

A complex task is underway at Lobs Hole to drill boreholes for the pipes that will house power, water and fibre optic cable for communications across three of the Snowy 2.0 sites.

Horizontal directional drilling (HDD) is being used to drill 2.2km-long boreholes from Lobs Hole to Marica. The holes are initially 300 millimetres in diameter and have an elevation difference of 650 metres. 

Two drilling operations are underway from top and bottom and will join up to create a continuous borehole before being enlarged to 660 millimetres in diameter.

This type of drilling is used for service lines that cross under waterways or underground structures and requires a high level of skill to maintain directional control while operating a drill string up to 1.8km long. Snowy 2.0 has contracted HDD experts Michels for the project.

The boreholes eliminate the need to construct approximately five kilometres of roads and excavate up to 60 metre cuts in the steep terrain, helping the Snowy 2.0 project team minimise environmental impacts. 

HDD techniques will also be used to take services under the Snowy Mountains Highway and waterways across the plateau through to the Tantangara worksite.

At Marica, the 28 metre diameter headrace surge shaft is now one-fifth of the way to its final depth of 263 metres and we’re starting drill and blast activities. There are two hoisting buckets called kibbles with a capacity of 25 tonnes for loading out excavated rock.

Excavators break up the rock with hydraulic hammers before it’s loaded into the kibbles and craned out of the shaft. The kibbles are lowered into hoppers and the rock drops into an articulated dump truck before being removed to a temporary stockpile area.

With the shaft now more than 50 metres deep, an integrated work platform and personnel hoist is being installed to provide worker access. We’ve installed ventilation ducts to manage air quality. 

At Talbingo, tunnelling of the tailrace adit is complete. TBM Lady Eileen Hudson is now excavating the tailrace tunnel alignment and heading towards the power station complex. This marks the start of the first power waterway on the Snowy 2.0 project. 

Excavation is ahead of schedule, with more than 26 metres recently excavated in a single day. The tailrace tunnel is six kilometres in length, with TBM excavation continuing through to mid-2025. 

Snowy 2.0 is being engineered to deliver clean and reliable energy storage and generation for the next 150 years. The target date for commercial operation of all units is December 2028, with first power expected in the second half of 2027. 

News

SNOWY 2.0 PROJECT – COMMUNITY INFORMATION SESSIONS IN NOVEMBER

02/11/2023

Interested in the latest updates from the Snowy 2.0 renewable energy mega project? 

Snowy Hydro and Snowy 2.0 principal contractor Future Generation Joint Venture are inviting local community members to attend information sessions being held throughout the Snowy Mountains in November. 

These in-person events enable locals to be updated about the project, ask questions and provide feedback. Hear from the Snowy 2.0 team about:

  • the recent project reset  
  • project progress, construction activities and news
  • traffic management, environment and safety
  • accommodation, recreation access and other local issues; 
  • local suppliers, jobs and training on Snowy 2.0.

Snowy Hydro CEO Dennis Barnes said with a significant public focus on Snowy 2.0 in recent months, the sessions provided opportunities to find out more directly from project team members.

“We are committed to being open and transparent with you – our local communities – about our  large and complex pumped-hydro project. A project of this scale and complexity has, and will, face challenges, but we continue to make solid progress across our construction and manufacturing operations. 

“Snowy 2.0 is being engineered to deliver clean and reliable storage and electricity generation for Australians for the next 150 years. It is a project that is generating jobs and significant investment in regional areas.

“I encourage everyone to come along to one of our community information sessions to hear the latest about Snowy 2.0, discuss any local concerns that you may have and ask questions.”

The Snowy 2.0 community information sessions in November will be held in Talbingo, Tumut, Tumbarumba, Cooma and Adaminaby. 

There will be some drop-in sessions, with the chance to speak one-on-one with project team members, and events featuring a formal presentation followed by community Q&As.

Community information sessions schedule:

Date Town and locationTime
Wednesday 8 November 2023
Wednesday 8 November 2023
Talbingo shops
Tumut River Brewing Co
12.00pm-2.00pm
6.00pm-7.30pm
Thursday 9 November 2023Near Tumbarumba IGA, The Parade12.00pm-2.00pm
Tuesday 14 November 2023Cooma Car Club6.00pm-7.30pm
Wednesday 15 November 2023Adaminaby Bowling Club6.00pm-7.30pm
News

NEW MAJOR PARTNERSHIP – SNOWY VALLEYS SCULPTURE TRAIL

23/10/2023

Engineering meets art on a grand scale, with Snowy Hydro CEO Dennis Barnes today announcing a new major sponsorship of the Snowy Valleys Sculpture Trail (SVST).

The SVST partnership includes funding from Snowy Hydro for seven new sculptures and a school education program aimed at delivering artist-led sculpture workshops to more than 1,500 school children in the Snowy Valleys Region.

“Snowy Hydro is proud to take on the role of Major Partner of the Snowy Valleys Sculpture Trail, a partnership that underscores our long-term, ongoing commitment to the local communities we operate in,” Dennis said.

“The Snowy Valleys Sculpture Trail is celebrated for its eye-catching outdoor art installations throughout the picturesque Snowy Valleys region and our support will enhance the trail’s reach, making it more accessible and engaging for both residents and visitors alike. We hope it will also draw more tourists to the region, thereby benefiting the local economy.”

The seven new Snowy Hydro-funded sculptures will be leased and installed over the next two years adding to the 35 existing artworks located between Adelong and Tooma, including the historic towns of Batlow, Talbingo and Tumbarumba. 

A key element of Snowy Hydro’s exciting partnership with SVST is the School Education Program. This program will bring artist-led sculpture workshops to 14 primary schools in the Snowy Valleys Region, along with two schools in Cooma and the Adaminaby Public School. Students will have the opportunity to immerse themselves in the world of art, creativity, and engineering through the added participation of Snowy Hydro engineers in the workshops.

Dennis emphasised the importance of the program, which aligned with Snowy Hydro’s education focus on science, technology, engineering and maths and engaging young people in activities that spark future careers.

“We believe that art and engineering go hand-in-hand, which is why they’re both core parts of our Next Generation Education Academy activities. Sculptures, like our hydroelectric projects, require a high level of engineering skill and creativity. 

“By exposing students to these artist-led workshops, we hope to inspire the next generation of engineers and artists right here in our local community.”

Snowy Valleys Sculpture Trail Founding CEO & Artistic Director David Handley expressed that:“It has been a humbling privilege to work with the local communities across the Snowy Valleys to create the Snowy Valleys Sculpture Trail as one of the most important cultural projects in regional Australia.  

“Snowy Hydro’s sponsorship means we are able to continue to deliver what we set out to do in providing the School Education Program for free to thousands of students across the Snowy Valleys, while building on the sculpture trail to offer visitors another reason to come back again and again to enjoy this stunning part of Australia.”

Snowy Hydro looks forward to working closely with the Snowy Valleys Sculpture Trail team and schools across the region to foster a deeper appreciation for art, engineering and innovation.

News

SNOWY 2.0 PROJECT UPDATE – SEPTEMBER 2023

05/10/2023

Following the recent announcement of the Snowy 2.0 project reset, the Snowy Hydro and Future Generation contractor teams are now a single team, working in close collaboration to achieve full commercial operation by December 2028.

The Snowy 2.0 Project Team is focused on excellent environmental outcomes while maintaining all-important safety principles. Safety is the number one priority for Snowy Hydro and core to the company’s values. High expectations for the management of all safety risks extend across the Snowy 2.0 project, without compromise.

Snowy 2.0 is critical to Australia’s transition to a low-carbon economy and when complete it will have broad-scale environmental benefits. Consistent with its responsible operation of the Snowy Scheme in Kosciuszko National Park for almost 70 years, Snowy Hydro is equally committed to minimising potential impacts from Snowy 2.0.

SAFETY PERFORMANCE
– As at September 2023, the project’s 12-month rolling TRIFR (Total Reportable Injury Frequency Rate) is 2.97, below the target of 4.0.**
– There has been a reduction in recordable and serious incidents on the project, with a focus on planning and a coordinated approach to safety management.
– Snowy 2.0 works closely with Comcare and SafeWork NSW and will continue to incorporate lessons learned and findings from the regulator into operational practices. 
**Calculated per million hours worked. Total hours worked to end September 2023: >17.7 million.

Construction of Snowy 2.0 will temporarily impact less than 0.1% of the park with any short-term unavoidable impacts rehabilitated throughout the project, in accordance with environmental project approvals. This includes around $100 million provided by Snowy Hydro to the offsets program for Kosciuszko National Park. Once operational, Snowy 2.0’s footprint within the park will be only 0.01%.

ENVIRONMENTAL PERFORMANCE
– 4 independent audits of the Snowy 2.0 project undertaken since project commencement. 
– 1,500 hours spent annually to proactively monitor the 163 biodiversity sites.
– More than 200 kilograms of native seed collected over three years for rehabilitation activities.
– 27 heritage site excavations and more than 35,00 indigenous artefacts salvaged and currently being documented, adding to the history of the Snowy Mountains Indigenous people. 

In this month’s update from the main worksite at Lobs Hole, Project Integration Manager Paul Smith recaps progress to date with over 40 per cent of Snowy 2.0 now complete, including:

  • Excavation of the 2.85 kilometre main access tunnel, lined with almost 13,000 locally manufactured concrete segments.
  • Excavation of the 2.9 kilometre emergency, cable and ventilation tunnel. 
  • Major upgrade of Ravine Road, the steep and winding 15 kilometre access road into Lobs Hole.
  • Infrastructure to support construction including the main yard workshops, worker campsites and more than 50 kilometres of access roads across three main worksites at Lobs Hole, Marica and Tantangara.

Excavation is underway of the huge 250 metre-long underground power station cavern and the tailrace tunnel, and TBM Kirsten is being modified to excavate the world-leading inclined pressure shaft. Drill and blast to create 11 cross passages and construction tunnels continues.

Above ground, there is plenty of activity across all sites. Lobs Hole Surface Works Project Manager Steve Lee helps ensure the Snowy 2.0 project is delivered in a safe and timely way, and to the quality standards and requirements of Snowy Hydro.

Surface works refers to a broad mix of activity such as haulage of spoil, maintenance of site roads, environmental controls, main yard area activity, office facilities and directional drilling, as well as the Talbingo intake build.

Latest progress on site includes Stage 2 earthworks with a recent blast covering an area of 4,500 square metres. About 10,000 cubic metres of material is being removed as the excavation of the 104-metre-high intake continues.

Snowy 2.0 is the largest renewable energy project under construction in Australia and will provide crucial deep storage central to Australia’s renewable transition. When complete, Snowy 2.0 will deliver 2,200 megawatts of dispatchable generation.

News

SNOWY HYDRO COMMUNITY GRANTS ROUND TWO – APPLICATIONS NOW OPEN

22/09/2023

Snowy Hydro is a long-time major supporter of communities and is proud to announce that the second round of the 2023 Snowy Hydro Community Grants Program is now open. 

Grants of up to $10,000 are available to support projects, local festivals, events and initiatives that benefit the local communities of the Snowy Mountains and surrounds.

In the first round of Snowy Hydro’s Community Grants Program earlier this year, there were more than 45 grant applications, with a total of $143,000 of funding distributed to 20 successful applicants.

The grants are available to a varied range of community groups, events and initiatives that align with Snowy Hydro’s four community commitment pillars of education and development, health and wellbeing, regional capacity building and environment.

Snowy Hydro CEO Dennis Barnes said “Snowy is proud of our ongoing commitment to communities and is pleased to provide positive, lasting outcomes and opportunities to the regions in which we live, work and serve.” 

“If you have a project, activity or event that benefits the local communities of the Snowy Mountains and surrounds, I encourage you to check your eligibility and apply!” Dennis said.

In order to be eligible for a grant, each application has to undergo a diligent assessment process to maintain consistency and transparency across the program. Before applying, please ensure your application aligns with Snowy Hydro’s Community Commitment Pillars and grant selection criteria. 

The proposed project or event should respond to a community need, provide tangible benefits to the community, strengthen the community by providing opportunities, demonstrate strong governance, foster strong and sustainable partnerships within the community and return value for investment. Importantly, applicant groups must be located within the Snowy Monaro or Snowy Valleys LGAs, or Corryong, Victoria, be a non-profit group or organisation that holds an Australian Business Number (ABN) and align with Snowy Hydro’s Values. All applications are to be submitted online via the online form, found on the Snowy Hydro website.

Applications for round 2 of the Snowy Hydro Community Grants Program must be received by Friday 15 October. Following the evaluation period, applicants will be advised of the outcome by 30 November 2022.

For more information about Snowy Hydro’s Community Grants Program visit: https://www.snowyhydro.com.au/communitygrantsprogram/

News

SECURING THE FUTURE OF CRITICAL ENERGY TRANSFORMATION PROJECTS

31/08/2023

Snowy Hydro today announced the outcomes of its major projects resets, for Snowy 2.0 and the Hunter Power Project. 

Snowy 2.0

  • Revised total cost to complete is $12 billion. At the end of June 2023, expenditure on the project was $4.3 billion, with 80% of these funds reinvested in the Australian economy. 
  • First power to be delivered in the second half of 2027 and a target date for commercial operation of all units of December 2028. 
  • The fixed-price EPC Contract was executed by Snowy Hydro and Future Generation Joint Venture (FGJV) following Final Investment Decision in a relatively benign and supportive environment.  The EPC Contract is no longer fit for purpose. 
  • Snowy Hydro and FGJV are finalising an amendment to the existing EPC Contract to move to an incentivised target cost contract model. Snowy Hydro will also settle all outstanding claims with FGJV. 
  • Delivery of an additional 200 MW or 10% capacity; bringing total capacity to 2,200 MW. 
  • Snowy 2.0 is the largest renewable energy project under construction in Australia and will provide crucial deep storage central to Australia’s renewable transition. 
  • The value of Snowy 2.0 to the national electricity market has increased materially since the Final Investment Decision in December 2018. 
  • Snowy 2.0 will provide 350,000 MWh of energy storage for 150 years. 
  • Snowy 2.0 remains value accretive, with the Company currently projecting a NPV of approximately $3 billion (based on a $12 billion revised target total cost and December 2028 delivery). 
  • Snowy Hydro is working closely with its Shareholder to develop an appropriate capital structure for the Company to support the increase in costs and to maintain the Company’s target credit rating of BBB+. 

HPP

  • The total target cost is now $950 million and will be funded by Snowy Hydro.
  • The project delivery remains December 2024. 
  • The project remains economically viable on a forward looking basis with the value of its firming capacity clearly demonstrated in the May/June 2022 energy crisis. 

Snowy Hydro CEO Dennis Barnes said the project resets will enable the commercially sustainable and successful delivery of both projects. 

“I am committed to ensuring these critically important projects are transparent and are placed on a robust and sustainable footing. Moving to an incentivised target model with FGJV will result in closer collaboration, stronger oversight and alignment of interests between Snowy Hydro and FGJV. ” Mr Barnes said. 

“Snowy 2.0 is being engineered to deliver clean and reliable storage and electricity generation for Australians for the next 150 years. It is a truly transformative national project that is generating jobs and significant investment in regional areas; it will deliver benefits immediately following its completion and will continue to do so for many future generations of Australians.

“Snowy 2.0 involves billions of dollars of investment, with approximately 80% going into Australian jobs, goods, services and skills. We are building the skills of local workers that can later be used elsewhere to assist in Australia’s ongoing energy transition.”   

“The Hunter Power Project is an important project in Australia’s energy transition, enabling the roll-out of wind and solar projects by firming these intermittent generation sources into reliable power,” Mr Barnes concluded.

Fact sheet 

Webuild Clough media statement

Background Information

Snowy Hydro today detailed the outcome of the review and reset process for key electricity projects, Snowy 2.0 and the Hunter Power Project.  

Snowy 2.0

The estimated total cost for Snowy 2.0 project delivery has been revised to $12 billion, with expenditure on the project to date of $4.3 billion. The terms of the contract with Future Generation Joint Venture (FGJV) are being finalised to move to an Incentivised Target Cost contract model, which will result in closer collaboration, stronger oversight and alignment of interests between Snowy Hydro and FGJV.  Snowy will also settle all outstanding claims with FGJV.

The target date for commercial operation of all units is December 2028 with first power to be delivered in the second half of 2027.

Through the project reset process Snowy Hydro has worked with FGJV and hydro technology contractor Voith Hydro to increase the capacity of the power station by 10%. Snowy 2.0 will now deliver dispatchable generation capacity of 2,200 MW, as well as providing energy storage of 350,000 MWh (or 160 hours of generation at maximum output). 

The cost revision reflects the compound effect of extraordinary factors. The external factors have impacted major projects around Australia and globally, in particular:

  • The major disruption caused by the Covid-19 pandemic; 
  • Delayed ability to mobilise, given critical shortages of skilled labour, exacerbated by quarantine and movement restrictions;
  • Extended and ongoing disruption to global shipping and supply chains caused by the pandemic, conflict and natural disasters, delaying access to key materials; 
  • Significant inflation in costs of key construction materials and inputs; and
  • Significant inflation in labour costs.  

In addition to the external factors, the project has been impacted by:

  • Design immaturity at final investment decision, with a number of design elements requiring more time to complete due to their technically complex nature. The final design now being more expensive to construct; and  
  • The impact of variable site and geological conditions, with the most impactful being the soft ground encountered that is delaying tunnel boring machine (TBM) Florence’s progress at Tantangara.

Despite the challenges outlined above, the project remains economic. Strong and growing market demand for dispatchable electricity is expected to underpin demand for the services provided by the project well into the future.

Construction of Snowy 2.0 is now approximately 40% complete and solid progress continues to be made, including:

  • Excavation of the main access and emergency cable and ventilation tunnels is now complete – approximately 6km of tunnelling;
  • Excavation on the 6km tailrace tunnel has commenced and tunnelling on the 1.45km inclined pressure shaft will commence shortly;
  • Work on the underground power station is now underway with access available from both ends and excavation and support of cavern crowns underway;   
  • Excavation at the Talbingo intake (where water will enter during pumping and exit during generation) is halfway complete, with 310,000m3 of earth excavated, while the first stage of earthworks at the Tantangara intake are complete, involving the movement of 205,000m3 of earth; and 
  • Manufacturing of the six pump turbines has commenced, the first major mechanical component has been shipped and has been transported to site.

Meanwhile, excavation of the headrace tunnel by TBM Florence is now ready to be continued, subject to the receipt of necessary regulatory approvals.

The project currently has a team of approximately 2,700 Australians dedicated to its safe and efficient delivery. An additional 1,500 jobs are forecast over the project’s lifespan.

Hunter Power Project

The Hunter Power Project has experienced similar challenges to Snowy 2.0 and following a comprehensive review the expected cost is now $950 million. Despite the increased cost the Hunter Power Project remains economic.

Construction continues to progress on schedule, with about 460 people working on the project, which remains on track to be delivered by December 2024. 

News

SNOWY HYDRO AND RED ENERGY SPONSOR KEEP AUSTRALIA BEAUTIFUL AWARDS

22/08/2023

Snowy Hydro and Red Energy are proud to announce the sponsorship of the Climate Change Mitigation & Adaptation category in the Keep Australia Beautiful NSW Tidy Towns & Sustainable Cities Awards. 

Keep Australia Beautiful NSW is a national non-profit organisation dedicated to promoting litter prevention, environmental sustainability and community engagement. 

Snowy Hydro CEO Dennis Barnes said the company’s sponsorship of the KAB NSW Tidy Towns & Sustainable Cities Awards would help increase awareness about how Snowy is supporting the transition to renewables in Australia. 

“We are proud to have lived, breathed and delivered renewable energy to Australians through the mighty Snowy Scheme for generations,” Dennis said. “We are committed to continuing this legacy and enhancing it.

“The combined Red Energy and Snowy Hydro support for the KAB partnership continues our consistent commitment to sustainability and the communities in which we live and work.”

Through its programs and campaigns, Keep Australia Beautiful NSW inspires individuals and communities to take action in preserving and enhancing the natural and built environments.

The Keep Australia Beautiful NSW Tidy Towns & Sustainable Cities Awards celebrate the achievements of communities that demonstrate outstanding environmental practices, social inclusivity, and economic viability. By sponsoring the Climate Change Mitigation & Adaptation category, Snowy Hydro and Red Energy aim to encourage and motivate communities to take proactive measures towards climate resilience and a clean energy future. 

This category focuses on recognising and rewarding local initiatives that address the challenges posed by climate change. These include the involvement of government and non-government organisations, community groups, businesses, schools, and individuals across NSW focusing on projects like renewable energy, enabling communities to adapt to a changing climate, and community engagement. 
For more information about the Keep Australia Beautiful NSW Awards and the Climate Change Mitigation & Adaptation category, please visit KAB NSW Sustainability Awards website.

News

TagEnergy and Snowy Hydro ink momentous renewable Power Purchase Agreement

21/08/2023

Snowy Hydro to purchase 40 percent of Golden Plains Wind Farm energy and green certificates

Global clean energy enterprise TagEnergy has signed a significant renewable Power Purchase Agreement (PPA), entering a deal that will see Snowy Hydro take 40 per cent of the energy and green certificates (LGCs) generated by the 756MW first stage of Golden Plains Wind Farm.

This transaction is the first PPA for the Golden Plains Wind Farm since the first stage of the 1,300MW mega project near Geelong, Victoria achieved financial close in November 2022 on a merchant basis, which was unique at the time. 

It comes as TagEnergy negotiates further PPAs for the project that has generated significant interest for its quality and location.

Franck Woitiez, Chief Executive Officer, TagEnergy said achieving financial close of Golden Plains Wind Farm East without the need for PPAs proved the effectiveness of its innovative investment approach.

“Now, this landmark PPA with Snowy Hydro proves our strategy to progressively contract the energy production during construction and operation. It also reflects the confidence major industry players like Snowy Hydro have in our large-scale renewables project expertise,” Mr Woitiez said.

“We are proud to enter this agreement with Snowy Hydro as we both work to ensure energy security and accelerate the transition to renewable energy as part of a rapidly growing industry,” he said.

The transaction has helped enable Snowy Hydro to secure a significant portion of its energy and LGC needs with a quality project that is at an advanced stage. 

Snowy Hydro Chief Executive Officer, Dennis Barnes, said “our partnership with TagEnergy is a significant step in supporting the decarbonisation of the National Electricity Market and further enabling Australia’s transition to renewables.”

Snowy Hydro Chief Commercial Officer, Gordon Wymer, added, “TagEnergy has succeeded in developing an investment structure that provided optimal outcomes for all stakeholders. This has enabled Snowy to continue to expand its ability to provide clean, green, cost-effective renewable energy to our customers, and paves the way for further cooperation with TagEnergy on other developments.”

Construction on the $2bn, 756MW stage one development featuring 122 turbines officially began in April 2023 following months of early works including road upgrades. It is expected to start producing renewable energy in the first quarter of 2025. 

The estimated annual emissions abatement is an average 770,000 tonnes CO 2 -e, or more than 23 million tonnes CO 2 -e over the project’s 30-year lifetime. 

News

SNOWY HYDRO SPONSORS TRADE DAY FOR YOUNG WOMEN

14/08/2023

Energised by electricity? Handy with a hammer? Nimble with numbers? Women keen to pick up the tools can find out more about an exciting new career at a trade day in Corryong sponsored by the Snowy Hydro Community Grants Program.

Hosted by Empowered Women in Trades (EWIT), the Tool Skills Day on Thursday 7 September aims to inspire local high school and TAFE students and other young women in Corryong to learn a skilled trade in the disciplines of civil, electrical and mechanical.

EWIT was one of 20 successful applicants receiving a total of $143,000 in funding from round one of the 2023 Snowy Hydro Community Grants. The highly successful program offers grants of up to $10,000 to support projects, festivals, events and initiatives which benefit the local communities of the Snowy Mountains and surrounds.

The EWIT proposal for a Tool Skills Day aimed at young women strongly aligns with Snowy Hydro’s community commitment pillar of education and development. 

Snowy Hydro CEO Dennis Barnes said fostering education opportunities and career pathways for local young people was a key focus for the company.

“We are committed to a diverse and inclusive workforce and we are keen to encourage young women into non-traditional roles like trades,” Dennis said. “At Snowy, we have a range of entry-level programs that provide a fantastic opportunity to get local young people straight from the classroom into an energising and practical career.

“We are very pleased to be supporting the EWIT Tools Skills Day at Corryong – where many of our Murray region staff live – through the Snowy Hydro Community Grants Program.”

The Tool Skills Day will be held in Corryong from 9.30am – 2.30pm on 7 September 2023. There will be hands-on EWIT workshops, an exploration of trades-based career pathways, the opportunity to chat one-on-one with ‘tradie ladies’ and more.  

Young local women interested in attending this fun, interactive event can register on the EWIT website. Places are limited, so get in quickly.

Local organisations can apply for funding from round two of the 2023 Snowy Hydro Community Grants Program. Applications open this month and must be submitted online via the Snowy Hydro website by 8 September.

All applications will be assessed against the program’s grants criteria – there is more information available on the website

Your proposed project or event must respond to a community need, provide tangible benefits to the community, strengthen the community by providing opportunities that align with Snowy Hydro’s community commitment pillars, demonstrate strong governance, foster strong and sustainable partnerships within the community and return value for investment.

**EWIT is an organisation that champions tradeswomen, diversity and gender equality. Its  mission is to transform the trades industry by empowering women and fostering a culture of inclusivity. EWIT works with education institutions and industry leaders to increase women’s participation in trades, provide opportunities for them to learn trade skills and assist them to thrive in the workforce.

News

SNOWY HYDRO PARTNERS WITH STARS FOUNDATION IN TUMUT

11/08/2023
Photo credit, Stars Foundation

Snowy Hydro is proud to announce a significant partnership with the Stars Foundation to support its new Tumut High School-based program that will deliver improved health, education and employment outcomes for local Indigenous girls and young women.

The three-year sponsorship for the inaugural Stars Foundation Tumut Program continues Snowy Hydro’s commitment to initiatives that support our local communities to develop and thrive.

Snowy Hydro CEO Dennis Barnes said the opportunity to assist the development of local Indigenous girls through the foundation’s intensive school-based mentoring was extremely important.

“This new sponsorship for the Stars Foundation will help Aboriginal and Torres Strait Islander girls in the Tumut region to realise their potential in all aspects of their development and wellbeing,” Dennis said. “We want to see these students shine.

“Snowy already has a successful partnership with the Clontarf Foundation in Tumut, which supports Indigenous boys to continue their schooling. 

“Enabling the Stars Foundation to deliver their mentoring and engagement programs to Indigenous young women in the same area is exciting for us.

“It’s not only about funding the Stars Foundation’s work – Snowy Hydro also has the chance to encourage students’ studies in science, technology engineering and maths (STEM) fields and highlight career pathways with Snowy through work experience, apprenticeships and traineeships.

“Snowy Hydro is a major employer and community supporter in the Snowy Mountains region, delivering many training and education opportunities, and we want to invest in the success of local people.

“We believe that by empowering these young Aboriginal and Torres Strait Islander women, Snowy Hydro is not only supporting students; but their families, communities and future generations.”

Established in 2015, the Stars Foundation provides a holistic mentoring program that supports more than 2,800 female First Nations students in primary and secondary schools across six states and territories. 

The Foundation’s key indicators have shown that through this program, there is an increase in school attendance (82% attendance) 13% higher than the Indigenous student average, resulting in over 90% of senior students completing Year 12 every year since Stars programs began. 85% of graduates successfully transition into further study or employment within six months of school completion.

News

SNOWY 2.0 PROJECT UPDATE – JULY 2023

28/07/2023

July marked an exciting milestone for Snowy Hydro, the Snowy 2.0 project and for one of its three tunnel boring machines. Tunnel boring machine (TBM) Lady Eileen Hudson was the first machine to start tunnelling on the pumped-hydro mega project, the first to complete a tunnel and is now underway on her second tunnel excavation.

Snowy 2.0 senior project manager, Rodd Brinkman, is onsite at the Talbingo adit, where teams have been preparing to relaunch TBM Lady Eileen into the mountain.

The TBM will excavate the 6km tailrace tunnel to connect Talbingo Reservoir to the underground power station complex. Water used to generate 2,000 megawatts of power from Snowy 2.0 will flow out of the tailrace tunnel. Water also enters this tunnel when the power station is pumping.

After completing the 2.8km main access tunnel (MAT) in 2022, it has been a big task to disassemble and safely extract TBM Lady Eileen and reassemble her with new components before commissioning. The conveyor stacker, grout batch plant, and chiller plant were also relocated from the MAT portal to the Talbingo adit.

Before a TBM begins her journey underground, it is traditional for the machine and crew to be blessed for a safe journey under the watch of St Barbara, the patron saint of tunnelling and underground work. The tradition of blessing is acknowledged at tunnelling sites all over the world.

Local parish priest Father Mark Croker blessed the TBM at an onsite ceremony with many Snowy 2.0 workers in attendance. The machine was then switched on and began cutting the rock face. This is the fourth TBM launch for Snowy 2.0 and a major achievement for the Snowy Scheme expansion project.

TBM Construction Manager Derek Whelan manages all Snowy 2.0 tunnelling activities, as well as the TBM construction personnel. He was on-hand to run through Lady Eileen’s impressive components, including a new 378-tonne cutterhead.

The cutterhead is made up of 70 cutting discs each weighing 290 kilos that will excavate the varying geology of the 11-metre diameter tunnel. At 137 metres in length and weighing 2,300 tonnes, the TBM is a moving factory with many parts working together in a complex operation.

More than 27,000 concrete segments manufactured at the Polo Flat, Cooma, precast facility will be used to line the tailrace tunnel with the segment erector, segment feeder, segment cranes, and sophisticated grouting system all onboard the TBM.

The TBM is also equipped with a guidance system that provides data to the machine’s pilot, to the nearest millimetre. This information is mirrored above ground and monitored by Snowy 2.0’s construction and engineering teams. 

Snowy 2.0: Underpinning Australia’s transition to a renewable energy future

 

News

SNOWY 2.0 TANTANGARA TUNNELLING UPDATE

28/07/2023

Successful ground stabilisation works and construction of a slurry treatment plant at Tantangara have been carried out by Snowy 2.0 teams prior to tunnel boring machine (TBM) Florence being able to restart excavation of the headrace tunnel.

Final commissioning tests are underway for the onsite slurry plant that means the dual-mode machine can switch from open excavation to a closed, pressurised mode. This method of excavation will enable stable excavation and efficient progress through softer ground conditions when required.

A significant testing regime has confirmed grouting and stabilisation of the loose material around TBM Florence has been effective. 

Additional stabilisation continues from the surface to solidify loose material above the machine and directly in front of the TBM cutterhead and the rock mass the machine is just short of.

We’re carrying out rotations of the cutterhead and minor advances of TBM Florence to ensure the machine is correctly positioned for final commissioning and to confirm the ground support activities are working.

Additionally we are working with NSW departments on environmental approvals for remediation of the surface depression above TBM Florence and to provide assurance that this will not reoccur. 

The plan is likely to go on public display in the coming weeks. 

The slurry treatment plant will process and separate materials used when the TBM is in closed excavation mode, including bentonite (an absorbent, swelling clay), which is placed into a tank and reused.