News

SNOWY 2.0 COST REASSESSMENT COMPLETE

22/10/2026
  • Target cost following contractor reassessment is $22.2 billion, with Snowy allowing for a cost scenario of $25 billion.
  • The project is now targeting to be fully commissioned in late 2029.
  • Machine tunnelling is 65% complete and cavern excavation 90% complete, with work to build the underground power station underway.
  • Snowy Hydro continues to strengthen oversight, controls and leadership to drive contractor productivity and cost performance, while prioritising safety.
  • Snowy Scheme expansion to provide long-duration energy storage equivalent to around 26 million home batteries, enough to power 3 million homes for a week.
  • GHD analysis shows substantial economic benefit, including the project adding $18.3 billion to the Australian economy. 
  • Snowy 2.0’s long-term asset life means it is predicted to reduce wholesale electricity prices by more than $7 billion to 2075.

Snowy Hydro today announced the updated target cost to complete Snowy 2.0 is $22.2 billion, with an allowance for a cost scenario of $25 billion, following a comprehensive cost reassessment by principal contractor Future Generation Joint Venture (FGJV). 

The higher cost scenario reflects Snowy 2.0’s uniqueness, risk and technical complexity, as well as FGJV’s cost estimation challenges.

Snowy Hydro CEO Dennis Barnes said the cost reassessment, which was subject to rigorous scrutiny and assurance by multiple layers of engineering cost experts, also updated the project’s schedule.

The new target completion date for Snowy 2.0 is late 2029.

The $22.2 billion target cost is not the amount that will have to be funded by taxpayers.

At the previous $12 billion cost estimate, around one-third or $4 billion, was Commonwealth investment in the company that Snowy Hydro did not need to repay.

The majority was funded by government and bank loans that as a profit-making business, Snowy must repay with interest, as well as Snowy’s own cashflows.

Work is underway on the Commonwealth’s preferred capital strategy at the new cost.

Mr Barnes said that while the cost increase is disappointing, the actions taken during the 2023 reset have protected the project from an even larger budget increase.

“I have no doubt that moving from a fixed price contract, which was never suitable for such scale, uniqueness and complexity, has protected the project from an even greater cost increase,” he said.

“It’s also likely that under a fixed price contract, the project would again be stopped under the weight of billions of dollars of claims from the contractor, as it was prior to the reset.”

Mr Barnes said the long term value of Snowy 2.0 to Australia’s energy reliability is stronger than ever.

“The scale of Snowy 2.0’s energy storage is world-leading. More than half of the total energy storage the grid needs by 2050 will come from Snowy 2.0 alone,” he said.

“Like the original Snowy Scheme, which still underpins energy reliability more than 70 years on, Snowy 2.0 is a generational investment in our energy sovereignty and a national asset owned by all Australians.”

The pumped hydro expansion of the Snowy Scheme will provide 350,000 megawatt-hours of storage, equivalent to around 26 million home batteries. 

“Snowy 2.0’s massive, long-duration storage will be the grid’s insurance policy against multi-day wind and solar droughts, helping to prevent blackouts and control price spikes that would otherwise flow through to household electricity bills,” he said.

An independent economic study conducted by GHD on the delivery and operation of Snowy 2.0 found widespread benefits to national and regional economies, including:

  • Generating significant economic activity, with around 80% of the project’s budget being spent in Australia.
  • Contributing $18.3 billion to the Australian economy during the delivery phase alone.
  • Reducing wholesale electricity costs by more than $7 billion to 2075.

The cost reassessment found the primary reasons for the increased project cost were: 

  • Detailed technical analysis continuing to identify the scale and nature of the design immaturity of the project when the final investment decision was made.
  • Construction complexities contributing to principal contractor FGJV not meeting productivity targets.
  • Cost and planning underperformance by FGJV leading to previous underestimating of the delivery scope.
  • Global cost escalation for equipment, services and people exceeding allowances made at the 2023 contract reset.

Snowy Hydro has taken action to strengthen the project’s delivery and cost performance, including:

  • Directing FGJV to establish a project control office with enhanced data and analytics to drive productivity and identify emerging risks early, which is now operational.
  • Embedding independent infrastructure delivery and cost experts in the project to bolster delivery oversight. 
  • Establishing a new board oversight committee including external megaproject advisors to monitor and take action on progress and risk.
  • Driving changes in FGJV’s leadership on the project, including a new Project Director, responsible for daily cost and schedule performance on the ground, and a broad uplift with more senior, globally experienced megaproject leaders.

The contract established at the 2023 reset has strong provisions that motivate FGJV to manage cost and program, and meet criteria relating to safety, environment and quality.

Snowy Hydro will use these mechanisms to drive the best project outcomes and value for money.

“We’re now much further through the project than at the 2023 reset, meaning we’ve learned more and more risk is behind us,” Mr Barnes said.

“At the reset, only 44% of the construction design had been completed, now it’s 96%.

“While there are still risks to manage, the project is in its strongest position yet.”

With more than 5,000 people currently working on the project, this year:

  • Underground power station construction has started, marking a new phase of Snowy 2.0’s development.
  • Decommissioning tunnel boring machine (TBM) Lady Eileen Hudson has started, after completing its second tunnel, following 8.6-kilometres of tunnelling.
  • TBM Florence is almost at the halfway point of its 15-kilometre tunnelling journey.
Work frontCurrent progressProgress at reset
Drill and blast tunnels95%20%
TBM tunnels65%19%
Power station complex excavation90%2%
Construction design96%44%
News

MAJOR BREAKTHROUGH ACHIEVED AS TBM MOMENTUM BUILDS

15/05/2026
  • Tunnel boring machine (TBM) Lady Eileen Hudson has achieved a significant milestone, successfully breaking through into the Snowy 2.0 underground cavern complex and marking the completion of her tunnelling operations.
  • Australia’s most talked about tunnel boring machine, TBM Florence, has been performing strongly for some time and is now approaching the halfway point on its 15-kilometre tunnelling journey. 
  • Australia’s largest renewable energy project continues to make progress, with the focus of the project transitioning to building the power station almost one kilometre underground.

A major milestone has been reached on Snowy 2.0, with TBM Lady Eileen Hudson completing excavation of a 6-kilometre tunnel and successfully breaking through into the underground cavern complex deep in the Snowy Mountains. 

Crucially, this breakthrough marks the completion of the massive 2,300-tonne machine’s tunnelling work on the project, having previously excavated a 2.85-kilometre access tunnel before the 6-kilometre tailrace tunnel, which will connect Snowy 2.0’s underground power station to the lower water reservoir, Talbingo Dam. 

Snowy Hydro CEO Dennis Barnes said the breakthrough is symbolic of the momentum being achieved at what is Australia’s largest renewable energy project.

“There’s nothing more exciting on a tunneling project than a breakthrough. Even more so with Snowy 2.0 because the geology we’re working with is extremely challenging,” Barnes said. 

“The ground under the Snowy Mountains is making us work for every metre, but like the original Snowy Scheme, it’s inspiring to see what Australia can achieve when we take on the hardest tasks.”

Adding to this tunnelling momentum, Australia’s most talked about tunnel boring machine has found a new lease of life, with TBM Florence’s performance issues now a distant memory as it approaches the halfway mark on its 15-kilometre journey.

Mr Barnes said Florence is now consistently achieving personal bests.

Snowy 2.0’s recently commissioned fourth tunnel boring machine, Monica, is one of the world’s most advanced. Custom-built to get through the complex geology of the Long Plain Fault Zone, Monica is excavating the opposite end of the same tunnel as Florence. 

The two machines will meet in the middle before being disassembled deep underground. 

Mr Barnes says the key to Snowy 2.0’s increasing momentum is the skill and dedication of its roughly 5000-strong workforce.

“Snowy 2.0’s people are proud of the work they’re delivering, the way they’re solving problems and delivering incredible feats of engineering every day,” he said.

“They’re also proud of the legacy their work is creating for Australia.

“Just like the original Snowy Scheme, the project is difficult and not without its setbacks. But when we’re done, we’ll have an incredible asset owned by every Australian to underpin energy reliability and security for generations.”

News

BIG RIG DRAWS BIG CROWD

14/10/2025

More than 1500 people converged on Cooma on Sunday, October 12 to welcome the latest Snowy 2.0 big rig – one of the largest traffic loads ever transported in NSW.

The main drive of TBM Monica – an integral component of the project’s fourth mega borer – drew an excited crowd of onlookers to Cooma town centre.

Spectators also flanked driveways and homes between Bredbo and Adaminaby to catch a glimpse of the big rig.

The convoy tipped the scales at a mammoth weight of more than 450 tonnes – across five trucks and a trailer, driven by 210 wheels across 35 separate axles.

Snowy Hydro Head of Social Impact and Community Sarah Norris described the transfer as a major milestone for both the project and the community.

“We were blown away by the attendance – it was a truly special evening, with an incredible atmosphere, as people lined the footpaths for the best vantage point to watch,” she said.

“It almost felt like a festival was taking place – we had free hot choccies and coffees and talented musician Leon Fallon on-hand to keep the crowd entertained

“Thanks to everyone who attended, we appreciate there were quite a few little people that stayed up past their bedtimes to witness a little piece of Snowy history.”

The mega transfer evoked memories for some community members of the mighty Thornycroft Antars hauling machinery and construction equipment through Cooma as part of the original Snowy Scheme decades ago.

There are 23 oversize loads being carefully planned and transported to Snowy 2.0 sites over the coming weeks associated with the assembly of TBM Monica.

News

TBM MONICA ON THE MOVE

03/10/2025

What weighs more than 137 tonnes, is seven metres wide and is transported by 152 wheels?

An integral piece of Snowy 2.0’s new tunnel boring machine’s cutterhead!

TBM Monica’s centre cutterhead piece was transported through Cooma last Wednesday night en-route to the Marica worksite north of Kiandra.

At 73 metres long, the transfer was a sight to behold as it travelled up Sharp Street bound for the final leg of its journey on the Snowy Mountains Highway.

Snowy Hydro Chief Delivery Officer – Snowy 2.0 Dave Evans said the smooth transfer was the result of months of hard work and planning.

“It’s an amazing sight to watch the huge pieces of our tunnel boring machine travel through Cooma and up to our remote Marica work site,” he said.

“It’s a credit to the project’s hard-working traffic and transport team that we’ve been able to complete this complex operation safely.”

The cutterhead – which is the main excavation tool of a TBM – is too large to move in one piece and has been split into five.

More than 140 big loads have been delivered to the Marica site from Port Kembla in recent weeks.

TBM Monica will become the project’s fourth active mega tunnelling machine, once it is assembled and commissioned in the coming months.

News

SNOWY HYDRO CELEBRATES $1 MILLION IN COMMUNITY GRANTS

15/09/2025

Snowy Hydro is celebrating a significant milestone, with more than $1 million donated to local organisations in the Snowy Monaro, Snowy Valleys and Towong regions through the Community Grants Program.

The major achievement highlights Snowy’s ongoing commitment to the communities it operates in and comes as the latest round of funding opens for applications.

Since 2022 the Community Grants Program, which is open to applications twice a year, has supported a diverse range of local organisations and grassroots initiatives, helping to make a tangible difference to rural communities.

Community groups and not for profit organisations across the Snowy Monaro, Snowy Valleys, and Towong regions are now invited to apply for funding. 

More than $200,000 in funding is available, with eligible applicants able to apply for grants of up to $10,000. 

Snowy Hydro Head of Social Impact and Community Sarah Norris said achieving $1 million in funding was a proud moment and a testament to the work of local organisations.

“This million dollar milestone represents hundreds of important local projects, from upgrades to local facilities, to new equipment for local hospitals. We’re incredibly proud of the organisations we support. 

“We’re looking forward to seeing what great ideas are submitted this round and we encourage any eligible group that has an initiative to apply.”

Earlier this year, more than 100 applications were received for the first round of funding in 2025 and this went to improving accessible living infrastructure in Cooma, support for the Tumbarumbra Spring Flower Festival, and the installation of security and technology upgrades at the Corryong Craft Shop. 

Funding from Snowy Hydro recently helped local wildlife rescue group, LAOKO, to purchase two large animal enclosures that will provide a safe and secure space for injured and orphaned wildlife to be rehabilitated. 

Robyn George, Treasurer, LAOKO, said that as a volunteer-run organisation, any funding they receive makes a huge difference to the outcomes for the native wildlife they care for. 

“We don’t receive recurrent government funding, so this kind of support is invaluable. Thanks to this funding from Snowy, our trained volunteers can give native wildlife the best possible chance of recovery before returning them to their natural environment.”

To be eligible for funding, community groups must be a not-for-profit or charity with an Australian Business Number and the project, event or initiative must directly involve or support communities located within the Snowy Monaro, Snowy Valleys or Towong local government areas.

Applications are open until 12 October 2025, with winners informed in late November. For more information and to apply, visit snowyhydro.com.au/communitygrantsprogram. 

News

SNOWY 2.0 POWERING OUR FUTURE-READY WORKFORCE

28/07/2025

Beyond building one of the most complex and challenging feats of engineering in the world, through its pumped hydro expansion to the iconic Snowy Scheme, Snowy 2.0 is also leaving a skills legacy.

Eight Year 12 students at Monaro High School have become the first NSW cohort to complete a school-based apprenticeship and traineeship (SBAT) program in supply chain operations, all while working on Australia’s largest renewable energy project.

The Cooma students spent one day a week gaining real-world insights and skills at the Polo Flat segment factory, serving as strong foundation for their careers.

Snowy Hydro CEO Dennis Barnes said the project would create a lasting skills legacy while securing Australia’s clean energy future.

“We are incredibly proud to empower local students by offering career-defining opportunities close to home on this once-in-a-generation project,” he said.

Monaro High School principal James Armitage said students embraced the opportunity to step into the workforce while still attending school.

“This SBAT partnership has shown how powerful it is when education and industry come together with a shared goal of supporting young people into meaningful careers,” he said.

News

KURRI KURRI FIRES UP FOR THE FIRST TIME

07/07/2025

Commissioning of Snowy Hydro’s fourth on-demand gas power station has achieved a significant milestone, with the Hunter Power Project (HPP) team successfully firing up one of the station’s two class-leading gas turbines late last week.

Snowy Hydro’s Chief Executive Officer Dennis Barnes said ‘first fire’ is an important milestone, which involves the gas turbine igniting and reaching full speed for the first time.

“First fire is a turning point in the power station’s development that confirms the design, construction and cold commissioning of the turbine has been successful,” Mr Barnes said.

“We’re very proud of the project team, whose hard work and dedication have seen us through a very challenging delivery program.”

To be known as Kurri Kurri Power Station in operation, the project’s gas supply infrastructure is now complete. The station is expected to reach full commercial operation in coming months after experiencing several periods of heavy rain over the past year.

The station’s commissioning program has been impacted by 69 days lost to weather impacts in 2025 alone, including during what was the region’s wettest May in 30 years.

Designed to run only for a minority of the time, when electricity demand is high and renewable generation is limited, Kurri Kurri Power Station will have capacity to provide a significant 660 megawatts of power to the grid. This will help reduce pressure on electricity prices, avoid blackouts and cut around five million tonnes of carbon dioxide-equivalent gas emissions annually.

”Every megawatt of capacity provided by Kurri Kurri enables three megawatts of renewable wind and solar to come online and replace increasingly unreliable coal generation,” Mr Barnes said.

“This represents real change in our energy system that will deliver important benefits to energy users across the grid, while making a difference in Australia’s response to climate change.”

Kurri Kurri Power Station remains on track to be delivered within its target cost of around $1.3 billion.

Video footage is available here, and images are available on request.

News

FOURTH TUNNEL BORING MACHINE ON WAY FOR SNOWY 2.0

07/07/2025

Green light for TBM to begin journey to Australia

Snowy Hydro is now preparing for the arrival of its fourth tunnel boring machine to join Snowy 2.0 – Australia’s largest renewable energy project.

This 178-metre long machine has been purpose-built to excavate a 5km tunnel through a complex geological area deep in the NSW Snowy Mountains, known as the long plain fault zone, that will eventually connect Tantangara reservoir with an underground power station built almost 1km underground. 

The TBM has now passed factory acceptance testing at Herrenknecht’s Guangzhou factory in China, ensuring all its major systems (mechanical, electrical, control and hydraulics) are validated and the machine is ready to be shipped to Australia.

The pumped hydro expansion to the iconic Snowy Scheme, Snowy 2.0’s incredible scale and power will translate 2200MW of capacity to 350,000 MWh of energy, taking the excess electricity produced by wind and solar during the day and delivering it to provide stability to our energy grid when it’s needed most.

Snowy Hydro Chief Delivery Officer – Snowy 2.0 David Evans said the project would play a pivotal role in enabling Australia’s transition to clean energy.

“Snowy 2.0 is essentially a giant battery, providing long-duration storage for wind and solar power to complement the short-duration storage that batteries provide,” he said.

“The successful completion of factory acceptance testing is testament to months of meticulous design, rigorous testing, engineering excellence and collaboration.”

News

SNOWY HYDRO’S 2025 COMMUNITY GRANTS PROGRAM NOW OPEN

03/03/2025

Community groups and not-for-profit organisations across Snowy Monaro, Snowy Valleys and Towong are invited to apply for funding to support local initiatives as part of Snowy Hydro’s Community Grants Program.

In total, Snowy Hydro has more than $200,000 of funding available to support this year’s program, with groups able to apply for grants of up to $10,000.  

Snowy Hydro’s Head of Social Impact and Community Sarah Norris said the Community Grants Program aims to support projects and initiatives that address local needs, connect communities, and deliver long lasting benefits.

“Strong communities are built on ideas, passion, and local action. This program is about just that, by empowering people to bring their ideas to life and make a lasting impact where it matters most,” she said.

“If you have an idea that could make a difference, we encourage you to apply. This support could help you turn your vision into a reality.”

In 2024, the Snowy Hydro community review panel assessed more than 180 applications across two funding rounds, allocating $405,000 to 60 impactful projects.

Past recipients include CUC Snowy Monaro, which used its grant to deliver the ‘Speak Up’ program – helping young people develop leadership and public speaking skills- and Big Brothers Big Sisters in Tumut, which expanded its mentoring program to support more at-risk youth.

To be eligible, groups must be not-for-profit or hold an Australian Business Number (ABN), and operate within the Snowy Monaro, Snowy Valleys or Towong local government areas.

Applications are open until 11.55pm on Sunday 16 March, with results announced by the middle of the year. 

For more details and to apply, visit snowyhydro.com.au/communitygrantsprogram/ 

The Snowy Hydro Community Grants Program was formalised in 2022, and since then has invested around $860,000 towards 142 local projects.

News

SNOWY HYDRO RELEASES 2024 SUSTAINABILITY REPORT

13/01/2025

Snowy Hydro has released its 2024 Sustainability Report, covering the progress the energy generator and retailer has made in areas such as environmental stewardship, social impact, and understanding and responding to its carbon emissions and climate risks.

Snowy Hydro CEO Dennis Barnes said the report reflects the company’s role in enabling Australia’s transition to renewable energy, while highlighting its progress and ambitions.

“At Snowy Hydro, we understand that sustainability goes beyond fulfilling our environmental commitments,” Mr Barnes said. 

“It’s about supporting our people, driving better diversity outcomes and making a positive difference to the communities we serve.

“The 2024 report shows the progress we are making and achievements we are proud of. While we recognise there is still more to do, this report serves as our roadmap, keeping us accountable and focused on delivering even better outcomes for stakeholders and the community in the future,” Mr Barnes said.

Mr Barnes also acknowledged Snowy Hydro’s responsibility as custodian of the water that flows through the Snowy Scheme, highlighting its role in balancing electricity network reliability, with the irrigation needs of farmers and other water users. 

Key sustainability achievements in the 2023/2024 financial year include:

  • Producing 3,937 GWh of renewable electricity from our hydro generation assets – enough energy to power around 600,000 homes for a year.
  • Growing our mass market retail brands business to 1.4 million customers, with a focus on delivering authentic, personal customer service.
  • Our retail brand Red Energy recognised with the Customer Satisfaction Award for the 14th year in a row
  • 7,958 students benefitting from Snowy STEM Academy programs
  • Keeping our people safe, reflected in our low Total Recordable Incident Frequency Rate (TRIFR) score
  • Delivering five events of 8-hour peak water flows from Jindabyne reservoir to improve the health of the Snowy River ecosystem
  • Maintaining outstanding reliability across our generation assets, with our hydro generators starting successfully 99.7 per cent of the time, and gas 98.5 per cent of the time, underpinning our ability to contribute to stable electricity supply
  • $557,000 spent through our community giving programs
  • Increasing the proportion of women in senior leadership roles
  • $320,000 of funding for Murray River rehabilitation work to maintain waterflow and prevent erosion 

Snowy Hydro is the third largest generator of electricity in Australia by capacity. We can generate 5,500 megawatts (MW) of electricity across eight hydroelectric power stations, three natural gas power stations, and four diesel power stations. 

Snowy 2.0 and the Hunter Power Project are set to deliver 2,860MW of additional capacity. This significant boost to the network’s capacity will make a meaningful difference to energy supply reliability, particularly on hot days in summer.

When these fast-start generating assets come online, they will enable further wind and solar generation that can displace more than 33 million tonnes of CO2-e per annum. 

This carbon emissions displacement would represent a 28 percent reduction in the National Electricity Market emissions from 2022 levels, and approximately 13 percent of Australia’s 2030 total emissions reduction target.

To learn more about Snowy Hydro’s sustainability journey and access the 2024 report, visit https://www.snowyhydro.com.au/wp-content/uploads/2025/01/Snowy-Hydro_2024-Sustainability-Report.pdf. 

News

SNOWY HYDRO CONTINUES INVESTMENT IN LOCAL COMMUNITIES

08/10/2024

Snowy Hydro has kicked off round two of its 2024 Community Grants Program, with more than $200,000 of funding available to help local community groups bring their ideas to life. 

With grants of up to $10,000 each, the program aims to support community-led initiatives that encourage growth and resilience in regional communities. Whether related to education, health, regional capacity building, or the environment, this funding is about creating lasting, positive change. 

Grants are available for community-led initiatives that align with Snowy Hydro’s community commitment pillars of education and development, health and wellbeing, regional capacity building and environment.

Sarah Norris, Snowy Hydro’s Social Impact and Engagement Manager, said the program is about helping communities thrive, “We believe in the future of our communities and are proud to support projects that create real opportunities and make a difference.

“The passion and creativity we’ve seen from past recipients have been truly inspiring, from grassroots initiatives that bring people together, to innovative programs that address regional challenges.

“It’s more than just funding. It’s about helping people turn their ideas into reality and contributing to a vibrant, resilient future for our region. We’re thrilled to continue this journey with a new round of applicants and can’t wait to see what ideas come through.”

Earlier this year, the first round saw over 80 applications, with $204,000 in funding for 30 worthy projects. From small grassroots efforts to larger initiatives, the Snowy Hydro Community Grants Program is making a real impact across the Snowy Mountains region.

To be eligible, groups must operate within the Snowy Monaro, Snowy Valleys, or Towong areas. They must be a non-profit group or organisation that holds an Australian Business Number (ABN) and can show how their project will address community needs, deliver lasting benefits, and build stronger connections.

Applications are open until 20 October 2024, with results announced in late November. For more details and to apply, visit the Snowy Hydro website and start making a difference today!

All applications must be submitted online via the online form, found on the Snowy Hydro website.
For more information about Snowy Hydro’s Community Grants Program visit: https://www.snowyhydro.com.au/communitygrantsprogram/

News

SNOWY 2.0 CONFIRMS FOURTH TUNNEL BORING MACHINE TO PROTECT DELIVERY TIMELINE

23/08/2024

A new tunnel boring machine will be deployed to help keep Snowy 2.0 on its delivery timeline, subject to approval by the NSW Department of Planning, Housing and Infrastructure.

New ground testing techniques have provided a better understanding of the full extent of a complex fault zone on the route of the 17 kilometre tunnel that will connect Snowy 2.0’s upper reservoir to its underground power station.

Snowy Hydro CEO Dennis Barnes said activating a fourth tunnel boring machine is the right course of action, given that what is now known about the tunnelling challenges ahead has provided the opportunity to mature the design.

“We’ve always known the fault zone was there and I’ve said in the past we will need to take action,” Mr Barnes said.

”While the fault zone is not a surprise, further ground testing since the project reset has revealed it is far more geologically challenging than earlier investigations indicated.

“We’ve carefully considered a range of options to get through the fault zone and overcome the initial design immaturity. Bringing in a fourth machine is the best way to keep the Snowy 2.0 on track for its target completion date of December 2028.”

A modification for Snowy 2.0’s project approval has been submitted to the NSW Department of Planning, Housing and Infrastructure, and will be subject to the Department’s independent community consultation and assessment processes.

The planning modification seeks approval for a change to construction methods within the project’s already approved work zone. There is no proposal to increase approved land clearing areas, surface or groundwater impacts. Local communities will be consulted about relevant changes to construction methodologies.

“We’re mindful that we are building Snowy 2.0 in a precious and protected national park. We have worked diligently to arrive at a proposal that does not step outside our existing construction area or increase our already approved impacts,” Mr Barnes said.

Mr Barnes said he remains committed to transparency regarding the project, given the inevitable challenges ahead.

“Just like the construction of the original Snowy Scheme, this is one of the most challenging and complex megaprojects underway in the world,” he said. 

“The fourth tunnel boring machine is an example of adapting to the situation in front of us, so we are doing everything we can to safely meet Snowy 2.0’s delivery timeline.”

While the need for a new tunnel boring machine is driven by new information about the fault zone, Mr Barnes acknowledges that the disappointing performance of Florence, the tunnel boring machine excavating the same tunnel that the new machine will also work on, has contributed to the need to take significant action.

“It’s difficult to say with certainty whether the same action would be needed if Florence had performed as we had hoped. However, it’s likely that the fourth machine would still be needed,” Mr Barnes said.

Snowy 2.0 will help underpin Australia’s transition to renewable energy through its ability to generate enough flexible, fast-dispatch energy to power 3 million homes continuously for a week. 

The unmatched scale and duration of Snowy 2.0’s storage and generating ability will effectively provide the network with critical electricity supply insurance against extended periods without enough wind and sunlight. Most other forms of storage, including batteries, can only generate power for a handful of hours. 

According to AEMO (the Australian Energy Market Operator), Snowy 2.0 will supply a majority of the National Electricity Market’s storage needs, greater than every other storage asset combined.

“Snowy 2.0 is critical to Australia’s energy future. We need to get this job done,” Mr Barnes said.

Subject to planning approval, the new machine will be tunnelling before the end of 2025.