Overhead Stringing

24/01/2025

November 2024

The overhead stringing of high voltage cables between the 132kV switch yard and the GSUT for both units was completed. This brings us one step closer to sending electrons to the grid as the 132kV conductors are the last component to send power to Ausgrid. The next step for the team is to await the connection of the 132kV switchyard on the HPP side to Ausgrid’s switch yard, KNSS. Overall, more than 3km of cabling will be used in these works.