February 2022
Earthworks for the gas-fired power station are well underway. Approximately 125,000 cubic metres of dirt and aggregates were moved on site to help build the construction pad. Approximately 6,750 cubic metres of dirt were excavated for the foundations for the gas turbine and generator.