News

Earthworks well underway

08/09/2023

February 2022

Earthworks for the gas-fired power station are well underway. Approximately 125,000 cubic metres of dirt and aggregates were moved on-site to help build the construction pad. Approximately 6,750 cubic metres of dirt were excavated for the foundations for the gas turbine and generator.

Connect with us