News

SNOWY 2.0 COST REASSESSMENT COMPLETE

22/10/2026
  • Target cost following contractor reassessment is $22.2 billion, with Snowy allowing for a cost scenario of $25 billion.
  • The project is now targeting to be fully commissioned in late 2029.
  • Machine tunnelling is 65% complete and cavern excavation 90% complete, with work to build the underground power station underway.
  • Snowy Hydro continues to strengthen oversight, controls and leadership to drive contractor productivity and cost performance, while prioritising safety.
  • Snowy Scheme expansion to provide long-duration energy storage equivalent to around 26 million home batteries, enough to power 3 million homes for a week.
  • GHD analysis shows substantial economic benefit, including the project adding $18.3 billion to the Australian economy. 
  • Snowy 2.0’s long-term asset life means it is predicted to reduce wholesale electricity prices by more than $7 billion to 2075.

Snowy Hydro today announced the updated target cost to complete Snowy 2.0 is $22.2 billion, with an allowance for a cost scenario of $25 billion, following a comprehensive cost reassessment by principal contractor Future Generation Joint Venture (FGJV). 

The higher cost scenario reflects Snowy 2.0’s uniqueness, risk and technical complexity, as well as FGJV’s cost estimation challenges.

Snowy Hydro CEO Dennis Barnes said the cost reassessment, which was subject to rigorous scrutiny and assurance by multiple layers of engineering cost experts, also updated the project’s schedule.

The new target completion date for Snowy 2.0 is late 2029.

The $22.2 billion target cost is not the amount that will have to be funded by taxpayers.

At the previous $12 billion cost estimate, around one-third or $4 billion, was Commonwealth investment in the company that Snowy Hydro did not need to repay.

The majority was funded by government and bank loans that as a profit-making business, Snowy must repay with interest, as well as Snowy’s own cashflows.

Work is underway on the Commonwealth’s preferred capital strategy at the new cost.

Mr Barnes said that while the cost increase is disappointing, the actions taken during the 2023 reset have protected the project from an even larger budget increase.

“I have no doubt that moving from a fixed price contract, which was never suitable for such scale, uniqueness and complexity, has protected the project from an even greater cost increase,” he said.

“It’s also likely that under a fixed price contract, the project would again be stopped under the weight of billions of dollars of claims from the contractor, as it was prior to the reset.”

Mr Barnes said the long term value of Snowy 2.0 to Australia’s energy reliability is stronger than ever.

“The scale of Snowy 2.0’s energy storage is world-leading. More than half of the total energy storage the grid needs by 2050 will come from Snowy 2.0 alone,” he said.

“Like the original Snowy Scheme, which still underpins energy reliability more than 70 years on, Snowy 2.0 is a generational investment in our energy sovereignty and a national asset owned by all Australians.”

The pumped hydro expansion of the Snowy Scheme will provide 350,000 megawatt-hours of storage, equivalent to around 26 million home batteries. 

“Snowy 2.0’s massive, long-duration storage will be the grid’s insurance policy against multi-day wind and solar droughts, helping to prevent blackouts and control price spikes that would otherwise flow through to household electricity bills,” he said.

An independent economic study conducted by GHD on the delivery and operation of Snowy 2.0 found widespread benefits to national and regional economies, including:

  • Generating significant economic activity, with around 80% of the project’s budget being spent in Australia.
  • Contributing $18.3 billion to the Australian economy during the delivery phase alone.
  • Reducing wholesale electricity costs by more than $7 billion to 2075.

The cost reassessment found the primary reasons for the increased project cost were: 

  • Detailed technical analysis continuing to identify the scale and nature of the design immaturity of the project when the final investment decision was made.
  • Construction complexities contributing to principal contractor FGJV not meeting productivity targets.
  • Cost and planning underperformance by FGJV leading to previous underestimating of the delivery scope.
  • Global cost escalation for equipment, services and people exceeding allowances made at the 2023 contract reset.

Snowy Hydro has taken action to strengthen the project’s delivery and cost performance, including:

  • Directing FGJV to establish a project control office with enhanced data and analytics to drive productivity and identify emerging risks early, which is now operational.
  • Embedding independent infrastructure delivery and cost experts in the project to bolster delivery oversight. 
  • Establishing a new board oversight committee including external megaproject advisors to monitor and take action on progress and risk.
  • Driving changes in FGJV’s leadership on the project, including a new Project Director, responsible for daily cost and schedule performance on the ground, and a broad uplift with more senior, globally experienced megaproject leaders.

The contract established at the 2023 reset has strong provisions that motivate FGJV to manage cost and program, and meet criteria relating to safety, environment and quality.

Snowy Hydro will use these mechanisms to drive the best project outcomes and value for money.

“We’re now much further through the project than at the 2023 reset, meaning we’ve learned more and more risk is behind us,” Mr Barnes said.

“At the reset, only 44% of the construction design had been completed, now it’s 96%.

“While there are still risks to manage, the project is in its strongest position yet.”

With more than 5,000 people currently working on the project, this year:

  • Underground power station construction has started, marking a new phase of Snowy 2.0’s development.
  • Decommissioning tunnel boring machine (TBM) Lady Eileen Hudson has started, after completing its second tunnel, following 8.6-kilometres of tunnelling.
  • TBM Florence is almost at the halfway point of its 15-kilometre tunnelling journey.
Work frontCurrent progressProgress at reset
Drill and blast tunnels95%20%
TBM tunnels65%19%
Power station complex excavation90%2%
Construction design96%44%
News

ANAO PERFORMANCE AUDIT: DELIVERY OF SNOWY 2.0

18/06/2026

Snowy 2.0 is our nation’s most critical energy project. Designed to operate for 150 years, it represents a generational investment in Australia’s energy sovereignty.

Snowy 2.0 will have an equivalent energy storage of around 26 million home batteries, providing more than half of the total energy storage the grid needs by 2050.

Snowy Hydro agrees with four of the ANAO’s five recommendations, covering enhanced documentation, reporting traceability and performance measurement within the existing governance framework. We partially agree with the remaining recommendation relating to public reporting.

While the recommendations do not propose fundamental changes to Snowy 2.0’s underlying delivery model, governance structure or management approach, we are committed to continually testing and improving our delivery oversight.

The report acknowledges that improvements in these areas have already been completed or are underway. The ANAO’s guidance informs many of these initiatives.

Many matters discussed in the report reflect deliberate commercial positions taken by Snowy Hydro to exercise our contractual rights and hold our principal contractor accountable on behalf of the Australian taxpayer.

Snowy Hydro remains committed to strong governance and oversight of Future Generation Joint Venture’s delivery of Snowy 2.0.

News

SNOWY 2.0 HONOURS SACRED TUNNELLING DAY

05/12/2025

The most sacred day for tunnellers, miners and underground workers was marked by a poignant Snowy 2.0 ceremony on December 4.

Workers gathered to celebrate St Barbara’s Day at the Marica worksite, metres away from TBM Monica – the huge new boring machine being assembled on the project.

The patron saint day itself stretches back centuries and is a tunnelling institution across the globe.

Statues are typically installed and blessed at new tunnel entrances, providing luck and safety for underground workers.

Indeed, the practice of naming TBMs after females is also inspired by St Barbara.

St Patrick’s Cooma parish priest Fr Mark Croker explained the significance of the patron saint’s story during the blessing ceremony.

“The story of St Barbara shows us the power of faith, it shows us the power of courage,” he said.

“For miners, these values were vital in their daily work and they remain inspiring for all of us in those difficult times all of us face daily.”

Snowy Hydro Chief Delivery Officer – Snowy 2.0 Dave Evans said December 4 was a special day.

“St Barbara’s Day means a lot to me and to our workforce … and is a way of recognising that while tunnelling is really challenging work, it’s about talking about both our successes and safety,” he said.

“While tunnellers can come across at times as perhaps as gruff people and tough people, there’s a lot of superstitions that run deep, especially in tunnelling.”

Mr Evans said an incredible amount of work had taken place to prepare for the launch of the new “monster” 200-metre long TBM in the new year.

“This machine is extremely complicated – its parts are sourced from across the world all needing to be pulled apart and pieced back together here on a remote construction site,” he said.

News

SNOWY FUNDING SAFEGUARDS TROUT INDUSTRY

29/10/2025

The first ground has been broken on a Snowy Hydro-funded extension to a world-class trout breeding facility in the Snowy Mountains that will help safeguard the industry for years to come.

The NSW Department of Primary Industry and Regional Development has received $5 million to construct a new 462sqm building at Gaden Trout Hatchery to house state-of-the-art aquaculture systems.

Monaro MP Steve Whan, NSW Agriculture Minister Tara Moriarty and Snowy Hydro General Manager of Water, Environment and Lands Charlie Litchfield break ground at the new trout facility.

Snowy Hydro General Manager of Water, Environment and Lands Charlie Litchfield said the investment was a core part of the Snowy 2.0 Recreational Fishing Management Plan.

“While we’re not in the business of breeding fish at Snowy Hydro, our partnership with the NSW Government and the Monaro Acclimitisation Society is fundamentally important to ensure the recreational impacts of the project are effectively mitigated,” he said.

“We’re working hard to ensure we’ve got a lasting positive impact on recreational fishing in the Snowy lakes – and this collaboration is crucial.”

Gaden manager Mitch Elkins said additional units to control water temperature and filtration would significantly increase the facility’s capability to produce up to 20 tonnes of larger rainbow and brown trout annually.

“This collaboration with Snowy Hydro will not only ensure we produce bigger and better fish but it will also safeguard the trout industry for years to come,” he said.

Construction is scheduled to begin in the new year, following tender award, and is expected to be completed by the end of June 2026.

News

HYDRO EXPERTS COLLABORATE, SHARE CHALLENGES

27/10/2025

The best and brightest minds in hydropower have visited Australia’s largest renewable energy project and explored the clean energy transition, as part of a major industry event hosted by Snowy Hydro.

The Hydro Power Engineering Exchange (HPEE) welcomed more than 110 experts from Australia, New Zealand, Malaysia and Canada to connect, share knowledge and technical presentations on their operations, maintenance and projects.

Essentially an asset-based engineering forum for technical staff, the biennial event first took place in 1990 as a joint initiative between the Snowy Mountains Authority (now Snowy Hydro), the Electricity Corporation of New Zealand and the Hydro Electric Commission of Tasmania (now Hydro Tasmania) and other Australian hydropower authorities.

This time around, three jam-packed days of conferences took place at QT Canberra from October 19-23 2025 sandwiched between a Snowy 2.0 site tour.

Snowy Hydro event convenor Jan de Groote described the exchange as “steeped in history and tradition” and unparalleled across the world.

“The networking opportunity for hydropower engineers results in an extremely knowledgeable peer network and long lasting engineering relationships between all participants.”

Snowy 2.0 Engineering and Quality General Manager Damon Miller said attendees were enthusiastic to see the successor to the Snowy Scheme up close.

“It’s always great to catch-up with colleagues to collectively discuss the challenges and opportunities associated with designing and building a new pumped hydropower project,” he said.

News

BIG RIG DRAWS BIG CROWD

14/10/2025

More than 1500 people converged on Cooma on Sunday, October 12 to welcome the latest Snowy 2.0 big rig – one of the largest traffic loads ever transported in NSW.

The main drive of TBM Monica – an integral component of the project’s fourth mega borer – drew an excited crowd of onlookers to Cooma town centre.

Spectators also flanked driveways and homes between Bredbo and Adaminaby to catch a glimpse of the big rig.

The convoy tipped the scales at a mammoth weight of more than 450 tonnes – across five trucks and a trailer, driven by 210 wheels across 35 separate axles.

Snowy Hydro Head of Social Impact and Community Sarah Norris described the transfer as a major milestone for both the project and the community.

“We were blown away by the attendance – it was a truly special evening, with an incredible atmosphere, as people lined the footpaths for the best vantage point to watch,” she said.

“It almost felt like a festival was taking place – we had free hot choccies and coffees and talented musician Leon Fallon on-hand to keep the crowd entertained

“Thanks to everyone who attended, we appreciate there were quite a few little people that stayed up past their bedtimes to witness a little piece of Snowy history.”

The mega transfer evoked memories for some community members of the mighty Thornycroft Antars hauling machinery and construction equipment through Cooma as part of the original Snowy Scheme decades ago.

There are 23 oversize loads being carefully planned and transported to Snowy 2.0 sites over the coming weeks associated with the assembly of TBM Monica.