Mini Hydro Developments
Jounama Small Hydro Power Station
Latest Information - June 2010
Civil Construction Works
Minor civil works on the power house access road and crane hard stand areas will commence mid June.  Minor re-profiling at the contractor compounds is scheduled to be completed by end of June. Re-vegetation of the site has commenced and will also be completed by the end of June.  The completion of these activities will signify the end of the civil works under this project
Electrical & Mechanical Plant Installation
Despite some challenging issues, the main plant commissioning phase is now complete.  The auxiliary plant has also been commissioned, but there are still a few minor aspects that need to be completed before handover.  These minor aspects will be completed by the end of June.  This completion of these activities will also signify the end of the main and auxiliary plant works under this project.
 